Present Status

  • Survey License

    Obtained on 2074/05/26

  • Feasibility Study

    Completed on 2075/11/25

  • Connection Agreement

    Signed on 2077/12/24

  • IEE

    Approved from Ministry on 2079/12/06

  • Detailed Project Report (DPR)

    Completed on 2080/01/01

  • Generation License

    Issued from DOED on 2081/03/31

  • PPA

    Signed on 2081/05/17

  • Construction Works

    Starting date 2081/06/29

  • Construction Completion

    24 months Time from Starting Date

  • Land required for Headworks and Powerhouse

    Acquired

  • Contractor selection for Civil works

    HM works and EM works is on going

  • Agreement Signed with Finman Service

    Financial Closure on 2081/05/16

  • Project Layout Excavation, Crusher Setup and Access Road construction

    On going