Present Status
-
Survey License
Obtained on 2074/05/26
-
Feasibility Study
Completed on 2075/11/25
-
Connection Agreement
Signed on 2077/12/24
-
IEE
Approved from Ministry on 2079/12/06
-
Detailed Project Report (DPR)
Completed on 2080/01/01
-
Generation License
Issued from DOED on 2081/03/31
-
PPA
Signed on 2081/05/17
-
Construction Works
Starting date 2081/06/29
-
Construction Completion
24 months Time from Starting Date
-
Land required for Headworks and Powerhouse
Acquired
-
Contractor selection for Civil works
HM works and EM works is on going
-
Agreement Signed with Finman Service
Financial Closure on 2081/05/16
-
Project Layout Excavation, Crusher Setup and Access Road construction
On going